Breaking news: Vietnam issues e-visa for all countries Read more »
close

Central expressway to be ready three months early

Last updated: tháng 8 15, 2023
On this page:

Construction of the 49-km Nha Trang - Cam Lam Expressway in the central region will finish in late May instead of September as scheduled.

The Nha Trang - Cam Lam Expressway Investment Company, Ltd.'s director said construction began in September 2021 amid Covid-19 outbreaks and rising building material prices. However, using modern technologies and having clear funding plans helped the company stay on schedule.

Over 95% of the four-lane expressway, which is expected to cost VND7.6 trillion (US$323.7 million), has been completed. It will run from Dien Khanh District in Khanh Hoa Province to Cam Thinh Tay Commune in the province’s Cam Ranh Town.

More information can be read on VnExpress.

Related Articles